COOM GREEN ENERGY PARK

Ørsted and FuturEnergy Ireland have come together to submit a proposal for an onshore renewable energy project near the Bottlehill and Glannasack areas in County Cork.

The planning application for Coom Green Energy Park was submitted in December 2020.

View our submitted proposals

COMMUNITY ENGAGEMENT


Further to extensive consultation with the local community, aplanning application was submitted in December 2020.

For more information on the proposals please get in touch with us:

 

PROJECT TIMELINE


MAR 2018

Door to door community consultation commenced

JUL 2018

Local community groups consultation commenced

Sep-Dec 2018

Community consultation and project layout refinement

Nov-Dec 2018

Community engagement sessions held

Feb 2019

Submission of two meteorological (met) mast planning applications to Cork County Council

Feb-Mar 2019

Door to door community consultation

MAY 2019

Two technical workshops held on Noise and Engineering: Grid, Construction, Transport and Storage

Jun-Jul 2019

Community consultation with second iteration of project layout / Surveying works ongoing

Sept - Oct 2019

Community workshops

Mar - Aug 2020

Revising layout

Nov 2020

Further consultation

Dec 2020

Application submission